GEM Detector Installation Programme
The installation programme for the GEM detector banks (subject to change) is as follows....
Bank | Angle | Made by | # modules | date operational | collimation installation |
5 | 90° | Outside | 18 | October 1999 | October 1999 |
2 | 20° | In-house/ Outside | 2 | October / December 1999 | June 2000 |
4 | 60° | In-house | 14 | 3 modules October 1999 11 modules - June 2002 |
June 2002 |
6 (6b) | 145° | Outside | 14 | Start February 2000, finish June 2000 | October 2000 |
7 (6a) | 160° | Outside | 10 | Start February 2000, finish June 2000 | October 2000 |
1 | 10° | Outside | 6 | August 2001 | not yet specified |
3 | 35° | Outside | 10 | Start June 2002 | Autumn 2002 |
0 | 5° | In-house | 1 | Autumn 2002 | - |
5X | 110° | Outside | 6 | January 2004 | October 2003 |
Last updated on 23 Jul 2004 by Alex Hannon (a.c.hannon@rl.ac.uk)